Wellington Building, Liverpool

Wellington Building, Liverpool

In the summer of 2016 Delta Glazing were approached by Colmore Tang to assist in a complete refurbishment programme for the windows in the building – without taking any off site – so all “in-situ”.

This involved:

  • grinding the paint and rust back to bright metal
  • a series of paints applied to specific RAL numbers
  • all broken glass was replaced
  • faulty and missing window furniture replaced
  • internal secondary glazing panels fitted

Many of the windows had been unable to be opened for many years due to painting and breakages in window furniture – so they required freeing and repairing.

The process was completed over several weeks. In addition we fitted mirrors to all 120 apartments in the building.